道路施工通告全封闭
(最新版)
编制人:__________________ 审核人:__________________ 审批人:__________________ 编制单位:__________________ 编制时间:____年____月____日
序言
下载提示:该文档是本店铺精心编制而成的,希望大家下载后,能够帮助大家解决实际问题。文档下载后可定制修改,请根据实际需要进行调整和使用,谢谢!
并且,本店铺为大家提供各种类型的实用范文,如文秘知识、条据书信、行政公文、活动报告、党团范文、其他范文等等,想了解不同范文格式和写法,敬请关注!
Download tips: This document is carefully compiled by this shop. I hope that after downloading it, it can help you solve practical problems. The document can be customized and modified after downloading, please adjust and use it according to actual needs, thank you!
In addition, this shop provides you with various types of practical sample essays, such as secretarial knowledge, article letters,
administrative official documents, activity reports, party and group sample essays, other sample essays, etc. If you want to know the format and writing of different sample essays, stay tuned!
第 1 页 共 4 页
正文内容
由于道路施工需要进行封闭,那么封闭就必须发出封闭道路的通告,你知道该怎么写吗下面本店铺给大家带来道路施工通告全封闭范文,供大家参考! 道路施工通告全封闭范文一 一、施工地点
X331翁金线K75+000~K75+800段(敕海庙~城北路),单幅计0.8公里。 二、施工时间
20XX年2月20XX年4月20XX年2月16日 道路施工通告全封闭范文二
因横江综合治理文昌桥工程梁板架设施工,施工期间(20XX年5月17日至20XX年6月30日)在滨江路与书院路交叉口至滨江路与黄山南路交叉口全路段实行交通全封闭,因受空间位置,且为确保行人行车安全和工程质量、进度,在施工期间禁止车辆通行。请车辆绕行,由此带来不便,敬请谅解。 谢谢合作。
xx县横江综合治理文昌桥项目部 xx镇
xx县交通管理大队 休宁县住建委
第 2 页 共 4 页
年5月17号
道路施工通告全封闭范文三 一、施工地点
X610南王线K0+000~K1+118段(南王线枫桥段),单幅计1.118公里;
X607王石线K7+400~K8+260段(仁祠堂桥~王石线新百左线交叉口),单幅计0.86公里;
X331翁金线K75+800~K80+000段(城北路交叉口~黄家堰公交站),单幅计4.2公里。 二、施工时间
X610南王线K0+000~K1+118段,20XX年9月19日至20XX年10月18日。
X607王石线K7+400~K8+260段,20XX年10月5日至20XX年11月19日。
X331翁金线K75+800~K80+000段,20XX年9月19日至20XX年12月5日。 三、施工内容
对上述路段进行路面大中修。 四、施工安排
对上述路段按全封闭方式进行施工。 五、注意事项
1、施工期间,禁止一切机动车辆通行,行经该路段的行人
第 3 页 共 4 页
及非机动车辆须注意安全。
2、施工现场按国家标准《道路交通标志和标线》规定设置有关的施工安全标志。
上述路段施工结束后,不另行通告。施工期间带来的不便请谅解。 xxxxx 年月日